Question: The Critical Path in a Project determines the; a . Shortest path to completion b . The probabilistic path to project duration c . The
The Critical Path in a Project determines the;
a Shortest path to completion
b The probabilistic path to project duration
c The most direct path to completion
d The deterministic path to project duration
e The longest path or expected project duration