Question: The critical path is A - C - F - H - J and the project duration is 3 0 days. ( Enter your response

The critical path is A-C-F-H-J and the project duration is 30 days. (Enter your response as a whole number.)
c. How much slack is in each of the activities G,H, and I?
Consider the following data for a project to install a new server at the Northland Pines High School:
\table[[Activity,Activity Time (days),Immediate Predecessor(s)],[A,3,-],[B,5,A],[C,6,A],[D,3,B],[E,1,B
 The critical path is A-C-F-H-J and the project duration is 30