Question: Activity Time ( weeks ) Immediate Predecessor ( s ) Activity Time ( weeks ) Immediate Predecessor ( s ) a m b a m

Activity
Time (weeks)
Immediate
Predecessor(s)
Activity
Time (weeks)
Immediate
Predecessor(s)
a
m
b
a
m
b
A
4
9
12
long dash
G
3
3
4
C, E
B
1
8
23
A
H
2
2
2
F
C
9
14
18
A
I
7
7
7
F
D
5
7
9
A
J
6
8
12
D, G, H
E
1
2
4
B
K
1
1
4
I, J
F
6
8
21
C, E
Part 2
a) The expected(estimated) time for activity C is
13.83 weeks. (Round your response to two decimal places.)
Part 3
b) The variance for activity C is
2.25 weeks. (Round your response to two decimal places.)
Part 4
c) Based on the calculation of the estimated times, the critical path is
A - C - F - H - J - K
.
Part 5
d) The estimated time for the critical path is
44.16 weeks. (Round your response to two decimal places.)
Part 6
e) The activity variance along the critical path is
11.53 weeks. (Round your response to two decimal places.)
Part 7
f) Using the standard normal tableLOADING..., the probability that Mbeki Construction will finish the project in 40 weeks or less is
enter your response here. (Enter as a probability and round your response to three decimal places.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!