Question: The critical path is A-C-E-G-I-J. Activity A B D E F G H 1 J Variance 0.25 0.20 0.25 0.25 3.36 0.69 0.11 0.11 1.78

The critical path is A-C-E-G-I-J. Activity A B D
The critical path is A-C-E-G-I-J. Activity A B D
The critical path is A-C-E-G-I-J. Activity A B D E F G H 1 J Variance 0.25 0.20 0.25 0.25 3.36 0.69 0.11 0.11 1.78 0.03 (a) Calculate the probability that the project will be completed in 31 weeks. (Round your answer to 4 decimal places, es 1.7945.) P(projects 31) - (b) Calculate the probability that the project will be completed in 35 weeks. (Round your answer to 1 decimal places, e.g. 1.7945.) P(projects 35)