Question: The critical path is the path through the schedule in which? Question 9 Select one: a . There are only finish - to - start
The critical path is the path through the schedule in which?
Question Select one:
a
There are only finishtostart relationships
b
There is no float
c
There are no leads or lags
d
Float is highest