Question: The Critical Path Method ( CPM ) is a scheduling technique used in construction projects. What does the critical path represent? a ) The sequence

The Critical Path Method (CPM) is a scheduling technique used in construction projects. What does the critical path represent?
a) The sequence of tasks with the most resources required
b) The longest sequence of tasks that determines the overall project duration
c) The tasks with the least amount of slack time
d) The tasks that can be delayed without impacting the project schedule?>?>