Question: The current conveyor - paced assembly - line configuration assigns the workers in the following way: Worker 1 : Tasks 1 , 2 , 3

The current conveyor-paced assembly-line configuration assigns the workers in the following way:
Worker 1: Tasks 1,2,3
Worker 2: Tasks 4,5,6
Worker 3: Tasks 7,8,9
Worker 4: Tasks 10,11,12
a. What is the capacity of the current line? (Round your final answer to two decimal places.)
Capacity
units per hour
b. What is the direct labor content? (Round your final answer to one decimal place.)
Direct labor content
min/unit
c. What is the average labor utilization (do not consider any transient effects such as the line being empti changes)?(Round your final answer to two decimal places.)
Labor utilization
%
 The current conveyor-paced assembly-line configuration assigns the workers in the following

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!