Question: The cycle time for unloading trucks at a Walmart Distribution Center is too long a generic pull process is to be designed and piloted to
The cycle time for unloading trucks at a Walmart Distribution Center is too long a generic pull process is to be designed and piloted to address the problems Given the following information: Average throughput is 1420 trucks/week Current PLT is 5.05 hr CVA time = 19 min Management has requested a PCE Target of 50% 7 days per week, 20.5 hours per day What should my WIP cap (in trucks) be? How many trucks should be unloaded before new trucks are accepted into the process?