Question: 2 3 . The CyClon project team has started gathering information necessary to develop a project network predecessor activities and activity time in days. The

23. The CyClon project team has started gathering information necessary to develop a
project networkpredecessor activities and activity time in days. The results of
their meeting are found in the following table:
Activity Description Duration Predecessor
1 CyClon Project
2 Design 10
3 Procure prototype parts 102
4 Fabricate parts 82
5 Assemble prototype 43,4
6 Laboratory test 75
7 Field test 106
8 Adjust design 67
9 Order stock components 108
10 Order custom components 158
11 Assemble test production unit 109,10
12 Test unit 511
13 Document results 312

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!