Question: The CyClon project team has started gathering the information necessary to develop a project network-predecessor activities and activity time in days. The results of their
The CyClon project team has started gathering the information necessary to develop a project network-predecessor activities and activity time in days. The results of their meeting are found in the following table:
| Activity | Description | Duration | Predecessor | |
| A | Design | 12 | ||
| B | Procure prototype parts | 11 | A | |
| C | Fabricate parts | 12 | A | |
| D | Assemble prototype | 4 | B, C | |
| E | Laboratory test | 10 | D | |
| F | Field test | 12 | E | |
| G | Adjust design | 10 | F | |
| H | Order stock components | 5 | G | |
| I | Order custom components | 8 | G | |
| J | Assemble test production unit | 10 | H, I | |
| K | Test unit | 8 | J | |
| L | Document results | 7 | K | |
The following all have a Start-to-Start relationship:
Procure prototype parts could start 7 days after the start of Design.
Fabricate parts could start 4 days after the start of Design.
Laboratory test could begin 1 day(s) after the start of Assemble prototype.
Field test could start 5 days after the start of Laboratory test.
Adjust design could begin 6 days after the start of Field test.
Order stock and Order custom components could begin 5 days and 5 days, respectively, after Adjust design.
Test unit could begin 7 days after the start of Assemble test production unit.
Document results could start 1 days after the start of Test unit.
Please include Network Diagram
| ||||||||||||||||||||||||