Question: The CyClon project team has started gathering the information necessary to develop a project network - predecessor activities and activity time in days. The results
The CyClon project team has started gathering the information necessary to develop a project networkpredecessor activities and activity time in days. The results of their meeting are found in the following table:
tableDuration Predecessor,ActivityDescription,BDesign,ACProcure prototype parts,ADFabricate parts,B C CELaboratory test,DFField test,EGAdjust design,FHOrder stock components,GIOrder custom components,GJAssemble test production unit,H IKTest unit,JLDocument results,K
Part A Draw the project network. Compute the early, late, and slack times for each activity.
tableWhat is the ES for Activity DWhat is the LF for Activity HWhat is the slack for Activity CWhat is the slack for Activity HWhat is the slack for Activity I?,,What is the length of the project?,,time periods.What is the critical path?,,
Part Upon further review the team recognize that they missed three finishtostart
lags. Procure prototype parts will involve only days of work but it will take days for
the parts to be delivered. Likewise, Order stock components will take days of work
and days for delivery and Order custom components will take days of work and
days for delivery. Reconfigure the CyClon schedule by entering the three finishtostart
lags.
What impact did these lags have on the original schedule?
What impact did these lags have on the amount of work required to complete the
project?
Part C Management is not happy with the schedule and wants the project completed
as soon as possible. Unfortunately, they are not willing to approve additional
resources. One team member pointed out that the network contained only finishto
start relationships and that it might be possible to reduce project duration by creating
starttostart lags. After much deliberation the team concluded that the following
relationships could be converted into starttostart lags:
Procure prototype parts could start days after the start of Design.
Fabricate parts could start days after the start of Design.
Laboratory test could begin days after the start of Assemble prototype.
Field test could start days after the start of Laboratory test.
Adjust design could begin days after the start of Field test.
Order stock and Order custom components could begin days and days,
respectively, after Adjust design.
Test unit could begin days after the start of Assemble test production unit.
Document results could start days after the start of Test unit.
Reconfigure the CyClon schedule by entering all nine starttostart lags.
The CyClon project team has started gathering the information necessary to develop a
project networkpredecessor activities and activity time in days. The results of their
meeting are found in the following table:
Part A Draw the project network. Compute the early, late, and slack times for each
activity.
Part Upon further review the team recognize that they missed three finishtostart
lags. Procure prototype parts will involve only days of work but it will take days for
the parts to be delivered. Likewise, Order stock components will take days of work
and days for delivery and Order custom components will take days of work and
days for delivery. Reconfigure the CyClon schedule by entering the three finishtostart
lags.
What impact did these lags have on the original schedule?
What impact did these lacs have on the amount of work required to complete the
project?
Part C Management is not happy with the schedule and wants the project completed
as soon as possible. Unfortunately, they are not willing to approve additional
resources. One team member pointed out that the network contained only finishto
start relatlonships and that it might be possible to reduce project duration by creating
starttostart lags. After much deliberation the team concluded that the following
relationships could be converted into starttostart lags:
Procure prototype parts could start days after the start of Design.
Fabricate parts could start days after the start of Design.
Laboratory test could begin day after the start of Assemble prototype.
Field test could start days after the start of Laboratory test.
Adjust design could begin days after the start of Field test.
Order stock and Order custom components could begin days and days.
respectively, after Adjust design.
Test unit could begin days after the start of Assemble test production unit.
Document results could start days after the start of Test unit.
Reconfigure the CyClon schedule by entering all nine starttostart lags.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock