Question: The CyClon project team has started gathering the information necessary to develop a project network-predecessor activities and activity time in days. The results of their
The CyClon project team has started gathering the information necessary to develop a project network-predecessor activities and activity time in days. The results of their meeting are found in the following table: Activity Description Duration Predecessor A Design 12 B Procure prototype parts 9 A C Fabricate parts 12 A D Assemble prototype 5 B, C E Laboratory test 9 D F Field test 12 E G Adjust design 12 F H Order stock components 11 G I Order custom components 6 G J Assemble test production unit 11 H, I K Test unit 8 J L Document results 6 K Part A. Draw the project network. Compute the early, late, and slack times for each activity.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
