Question: The data given in the Table describes the charges for a crew responsible for a pipeline. The operation work-schedule is 510 (i.e., 5 days 10
The data given in the Table describes the charges for a crew responsible for a pipeline. The operation work-schedule is 510 (i.e., 5 days 10 hrs per day) and overtime is counted as time and one half. FICA and unemployment taxes are 6.25% and 2.8%, respectively. No. Question Answer 1 Total hourly cost (\$/crew-hour) for the crew 2 Total hourly cost ( $/ man-hour) for the crew 3 Total weekly cost (\$/week) for the crew