Question: Y5 The data given in the Table describes the charges for a crew responsible for a pipeline. The operation work-schedule is 5 x 10 (i.e.,
Y5

The data given in the Table describes the charges for a crew responsible for a pipeline. The operation work-schedule is 5 x 10 (i.e., 5 days x 10 hrs per day) and overtime is counted as time and one half. FICA and unemployment taxes are 6.25% and 2.8%, respectively. Crew Size Trade Base S/hr WC PL&PD ($/$100) $/$100) F.B.($ Foreman 27.25 10.5 3.89 2.00 Welder 23.45 11.85 4.5 1.15 Helper 15.23 11.95 4.95 0.85 Operator 25.12 12 4.8 1.50 Quality 29.50 8.6 2.7 1.8 Safety 28.20 8.2 2.8 1.3 No. Question Answer 1 Total hourly cost ($/crew-hour) for the crew 2 Total hourly cost ($/man-hour) for the crew 3 Total weekly cost ($/week) for the crew