Question: The data in the table below represent time study observations for a woodworking operation. ( Hint: See Solved Problems section. ) OBSERVATIONS ( minutes per

The data in the table below represent time study observations for a woodworking operation. (Hint: See Solved Problems section.)
OBSERVATIONS (minutes per cycle)
Element Performance
Rating 123456
1110%1.201.171.161.221.241.15
21150.830.870.780.820.851.32*
31050.580.530.520.590.600.54
Click here for the Excel Data File
*Unusual delay, disregard time.
a. Based on the observations, determine the standard time for the operation, assuming an allowance of 15 percent of job time. (Round your intermediate calculations and final answers to 3 decimal places.)\

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!