Question: the data is Consider the project scheduling and budget data shown below. The data is reported at the end of its sixth week. table

the data is Consider the project scheduling and budget data shown below. The data is reported at the end of its sixth week.
\table[[Activity,\table[[Predex],[cessura]],\table[[Dura-],[tion],[(\pi ks)]],\table[[Budget],[($)]],\table[[Actual],[Cost],[($)]],\table[[%],[Com-],[plete]]],[a,-,2,300,400,100],[b,-,3,200,160,100],[\epsi ,a,2,250,300,100],[d,a,5,600,400,20],[e,b_(1)c,4,400,200,20]](Using the task letter with no spaces) The critical path for the project .......and has a duration of ......weeks