Question: The debits to Work in Process - Assembly Department for April, together with data concerning production, are as follows: April 1, work in process: Materials

The debits to Work in Process - Assembly Department for April, together with data concerning production, are as follows:

April 1, work in process:
Materials cost, 3,000 units $7,302
Conversion costs, 3,000 units,
2/3 completed $5,183
Materials added during April, 10,000 units $25,533
Conversion costs during April $32,123
Goods finished during April, 11,500 units - - -
April 30 work in process, 1,500 units,
1/2 completed - - -

All direct materials are placed in process at the beginning of the process and the first-in, first-out method is used to cost inventories. What is the materials cost per equivalent unit for April?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!