Question: The demand for a product ( A ) is 8 0 0 parts per day and A is produced in a machining cell. The total

The demand for a product (A) is 800 parts per day and A is produced in a machining cell. The total wait time for producing A is 0.3 hours, the machine setup time is 0.2 hours per container, and the processing time is 0.02 hours. The kanban container capacity is 80 units. How many production kanbans are needed? What is the inventory size?