Question: The demand for subassembly S is 1 5 0 1 5 0 units in week 7 . Each unit of S requires 2 2 unitss

The demand for subassembly S is
150150
units in week 7. Each unit of S requires
22
unitss
of T and
11
unitnothing
of U. Each unit of T requires
22
unitss
of V,
22
unitss
of W, and
11
unitnothing
of X. Finally, each unit of U requires
22
unitss
of Y and
22
units of Z. One firm manufactures all items. It takes 2 weeks to make S,
11
weeknothing
to make T,2 weeks to make U,
22
weekss
to make V,
33
weeks to make W,
11
weeknothing
to make X,2 weeks to make Y, and
11
weeknothing
to make Z.
LOADING...
Click the icon to view the product structure and the time-phased product structure.
LOADING...
Click the icon to view the on-hand inventory.
Part 2
Suppose that in addition to
150150
units of S, there is also a demand for
2020
units of U, which is a component of S. The
2020
units of U are needed for maintenance purposes. These units are needed in week 6. Additionally, a new order has been received for
9090
units of S due in week 8. Modify the net material requirements plan to reflect these changes.
Part 3
Construct a new net material requirements plan
(enter
your responses as whole
numbers).
The demand for subassembly S is 1 5 0 1 5 0 units

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!