Question: The demand for subassembly S is 1 5 0 1 5 0 units in week 7 . Each unit of S requires 2 2 unitss

The demand for subassembly S is
150150
units in week 7. Each unit of S requires
22
unitss
of T and
11
unitnothing
of U. Each unit of T requires
11
unitnothing
of V,
22
unitss
of W, and
11
unitnothing
of X. Finally, each unit of U requires
11
unitnothing
of Y and
22
units of Z. One firm manufactures all items. It takes 2 weeks to make S,
11
weeknothing
to make T,2 weeks to make U,
11
weeknothing
to make V,
33
weeks to make W,
11
weeknothing
to make X,2 weeks to make Y, and
22
weekss
to make Z.
LOADING...
Click the icon to view the product structure and the time-phased product structure.
Part 2
In addition to
150150
units of S, there is also a demand for
3030
units of U, which is a component of S. The
3030
units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used).
Week
Lead Time
Item
Order release
The demand for subassembly S is 1 5 0 1 5 0 units

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!