Question: The demand for subassembly S is 1 5 0 units in week 7 . Each unit of S requires 2 units of T and 2

The demand for subassembly S is 150 units in week 7. Each unit of S requires 2 units of T and 2 units of U. Each unit of T requires 2 units of V,1 unit of W, and 2 units of x. Finally, requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S,1 week to make T,2 weeks to make U,2 weeks to make V,3 weeks to make W,1 make x,2 weeks to make Y, and 1 week to make Z.
Click the icon to view the product structure and the time-phased product structure.
Click the icon to view the on-hand inventory.
Suppose that in addition to 150 units of S, there is also a demand for 30 units of U, which is a component of S. The 30 units of U are needed for maintenance purposes. These units a week 6. Additionally, a new order has been received for 70 units of S due in week 8. Modify the net material requirements plan to reflect these changes.
Construct a new net material requirements plan (enter your responses as whole numbers).
 The demand for subassembly S is 150 units in week 7.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!