Question: The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U.
The demand for subassembly S is 100 units in week 7. Each unit of S requires
1
unit
of T and
2
units
of U. Each unit of T requires
1
unit
of V,
2
units
of W, and
1
unit
of X. Finally, each unit of U requires
2
units
of Y and
3
units of Z. One firm manufactures all items. It takes 2 weeks to make S,
1
week
to make T, 2 weeks to make U,
2
weeks
to make V,
3
weeks to make W,
1
week
to make X, 2 weeks to make Y, and
1
week
to make Z.
LOADING...
Click the icon to view the product structure and the time-phased product structure.
Construct a gross material requirements plan (type 0 if the input box is not used).
| Week | Lead Time | ||||||||
| Item | 1 | 2 | 3 | 4 | 5 | 6 | 7 | (weeks) | |
| S | Gross req | nothing | nothing | nothing | nothing | nothing | nothing | nothing | |
| Order release | nothing | nothing | nothing | nothing | nothing | nothing | nothing | 2 | |