Question: The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U.

The demand for subassembly S is 100 units in week 7. Each unit of S requires

1

unit

of T and

2

units

of U. Each unit of T requires

1

unit

of V,

2

units

of W, and

1

unit

of X. Finally, each unit of U requires

2

units

of Y and

3

units of Z. One firm manufactures all items. It takes 2 weeks to make S,

1

week

to make T, 2 weeks to make U,

2

weeks

to make V,

3

weeks to make W,

1

week

to make X, 2 weeks to make Y, and

1

week

to make Z.

LOADING...

Click the icon to view the product structure and the time-phased product structure.

Construct a gross material requirements plan (type 0 if the input box is not used).

Week

Lead Time

Item

1

2

3

4

5

6

7

(weeks)

S

Gross req

nothing

nothing

nothing

nothing

nothing

nothing

nothing

Order release

nothing

nothing

nothing

nothing

nothing

nothing

nothing

2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!