Question: The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U.

The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 1 unit of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 1 unit of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 2 weeks to make T, 2 weeks to make U, 1 week to make V, 2 weeks to make W, 2 weeks to make X, 2 weeks to make Y, and 1 week to make Z.

Click the icon to view the product structure and the time-phased product structure.

Construct a gross material requirements plan (type 0 if the input box is not used).

Week

Lead Time

Item

1

2

3

4

5

6

7

(weeks)

S

Gross req

enter your response here

enter your response here

enter your response here

enter your response here

enter your response here

enter your response here

enter your response here

Order release

enter your response here

enter your response here

enter your response here

enter your response here

enter your response here

enter your response here

enter your response here

2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!