Question: The demand for subassembly S is 90 units in week 7. Each unit of S requires 1 unit of T and 2 units of U.
The demand for subassembly S is 90 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 2 units of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 1 unit of Y and 3units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z.
Suppose that in addition to 90 units of S, there is also a demand for 30 units of U, which is a component of S. The 30 units of U are needed for maintenance purposes. These units are needed in week 6. Additionally, a new order has been received for 80 units of S due in week 8. Modify the net material requirements plan to reflect these changes.
Construct a new net material requirements plan (enter your responses as whole numbers).
| Item | Week | Lead Time | ||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | (weeks) | ||
| S | Gross req | 2 | ||||||||
| On hand | ||||||||||
| Net req | ||||||||||
| Order receipt | ||||||||||
| Order release | ||||||||||
| Item | On-Hand Inventory | Item | On-Hand Inventory |
| S | 20 | W | 25 |
| T | 20 | X | 25 |
| U | 30 | Y | 110 |
| V | 20 | Z | 40 |