Question: The demand for subassembly S is 90 units in week 7. Each unit of S requires 1 unit of T and 2 units of U.

The demand for subassembly S is 90 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 2 units of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 1 unit of Y and 3units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z.

Suppose that in addition to 90 units of S, there is also a demand for 30 units of U, which is a component of S. The 30 units of U are needed for maintenance purposes. These units are needed in week 6. Additionally, a new order has been received for 80 units of S due in week 8. Modify the net material requirements plan to reflect these changes.

Construct a new net material requirements plan (enter your responses as whole numbers).

Item

Week

Lead Time

1

2

3

4

5

6

7

8

(weeks)

S

Gross req

2

On hand

Net req

Order receipt

Order release

Item

On-Hand Inventory

Item

On-Hand Inventory

S

20

W

25

T

20

X

25

U

30

Y

110

V

20

Z

40

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!