Question: The demand for subassembly S is units in week 7. Each unit of S requires unit of T and unit of U. Each unit of
The demand for subassembly S is units in week 7. Each unit of S requires unit of T and unit of U. Each unit of T requires unit of V, unit of W, and unit of X. Finally, each unit of U requires unit of Y and units of Z. One firm manufactures all items. It takes 2 weeks to make S, week to make T, 2 weeks to make U, week to make V, weeks to make W, week to make X, 2 weeks to make Y, and week to make Z.
Click the icon to view the product structure and the time-phased product structure.

Click the icon to view the on-hand inventory.

Construct a net material requirements plan using on-hand inventory (enter your responses as whole numbers).

^Above is what I need filled out. Thanks!
i More Info The product structure. The time-phased product structure. Level V 0 S W T X T(1) U (2) S 1 Y U N 2 X(1) Y(2) Z(3 1 1 6 2 3 4 5 Time in weeks Print Done More Info Item S T U On-Hand Inventory 20 20 30 30 Item W Y Z On-Hand Inventory 30 30 380 40 Print Done Week Lead Time (weeks) Item 1 2 3 4 5 6 7 S Gross req On hand Net req 2 Order receipt Order release i More Info The product structure. The time-phased product structure. Level V 0 S W T X T(1) U (2) S 1 Y U N 2 X(1) Y(2) Z(3 1 1 6 2 3 4 5 Time in weeks Print Done More Info Item S T U On-Hand Inventory 20 20 30 30 Item W Y Z On-Hand Inventory 30 30 380 40 Print Done Week Lead Time (weeks) Item 1 2 3 4 5 6 7 S Gross req On hand Net req 2 Order receipt Order releaseStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts