Question: The _ _ _ _ _ _ _ _ design phase is complete when the design is approximately 3 0 percent complete. Question 1 options:

The ________ design phase is complete when the design is approximately 30 percent complete.
Question 1 options:
Schematic
Conceptual
Design development
Engineering
None of the above
Question 2(Mandatory)(1 point)
Saved
Unless otherwise specified, the specifications normally take precedence over:
Question 2 options:
Codes.
Drawings.
Change orders.
Agreement
None of the above.
Question 3(Mandatory)(1 point)
Saved
The CM's site office is usually responsible for which duties?
Question 3 options:
Inspect all work
Coordinate and schedule work
Write daily reports
All of the above
Question 4(Mandatory)(1 point)
Saved
A project manager may direct a change in the Work when such change is authorized in writing by:
Question 4 options:
The owner.
A code requirement.
A subcontractor.
The Builder.
A Supplier.
Question 5(Mandatory)(1 point)
Saved
A pre-construction meeting should be held:
Question 5 options:
During the bid phase
After agreement but before Notice to Proceed
Prior to advertising for bids
After bid opening but after award of the contract
After Notice to Proceed
Question 6(Mandatory)(1 point)
Saved
The final decision regarding additions, deductions, and alternates in the Contract rests with:
Question 6 options:
The Project Manager
The Contractor.
The Consultants
The Construction Manager
None of the above
Question 7(Mandatory)(1 point)
Saved
The Project Manager may reject materials or work if:
Question 7 options:
If they do not like the containers they came in
It does not comply with the specifications
They do not approve of the manufacturer
The contractor did not get approval from the building inspector beforehand
Both B and D
None of the above
Question 8(Mandatory)(1 point)
Saved
Authorization to the contractor to perform work which involves a deviation from the requirements of the Contract Documents is called an:
Question 8 options:
Addendum
Alternate
New contract
Change order
None of the above
All of the above
Question 9(Mandatory)(1 point)
Saved
The term "substantial completion," unless redefined in the Contract Documents, normally means that:
Question 9 options:
The work is almost completed, but final completion will not occur until a later date
The contractor's obligations under the contract have been satisfied even though some minor items of pickup work remain
Liquidated damage provisions of the contract still apply until all pickup (punch list) work is completed
The architect or engineer may not process final payment until a certificate of "final completion" is executed.
Both A and B
Both C and D
Question 10(Mandatory)(1 point)
Saved
In which document is the contractor most likely to find the requirements for the type of material required to be used in the work?
Question 10 options:
Plans
Specifications
Change Order
Bulletin
Question 11(Mandatory)(1 point)
Saved
In order to consider a $2,651,000 project substantially completed, the value of any un-finished or deficient items must not exceed:
Question 11 options:
$41,510.00
$79,530.00
$ 1,000.00
$26,510.00
Question 12(Mandatory)(1 point)
Saved
For a $250,000 project, it is deemed complete when the value of the deficiencies is less than
Question 12 options:
$ 2,500.00
$ 7,500.00
$ 1,000.00
$ 500.00

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!