Question: The difference between actual costing and normal costing is ________. A. normal costing uses budgeted indirectminuscosts B.normal costing uses actual quantities of directminuscosts C.actual costing
The difference between actual costing and normal costing is ________.
A. normal costing uses budgeted indirectminuscosts
B.normal costing uses actual quantities of directminuscosts
C.actual costing uses actual quantities of costminusallocation bases
D.actual costing uses actual quantities of directminuscosts