Question: The difference between calculating project time estimates using the PERT method vs the Critical Path Method ( CPM ) is PERT's activity time estimates are

The difference between calculating project time estimates using the PERT method vs the Critical Path Method (CPM) is
PERT's activity time estimates are certain, with no variability
CPM uses a probability distribution for activity times to allow for variability
PERT uses a deterministic distribution for activity times to allow for variability
PERT uses a probability distribution for activity times to allow for variability