Question: The difference between the earned value ( EV ) and the actual cost ( AC ) is known as the schedule variance ( SV )
The difference between the earned value EV and the actual cost AC is known as the
schedule variance SV
cost variance CV
cost performance index CPI
schedule performance index SPI