Question: Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV: Timeframe = 10 days AC = EV = At the End of the 5th
Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV: Timeframe = 10 days AC = EV = At the End of the 5th day 4 chairs were Completed at a cost of $11.00 each CV CPI SV = SPI To install a 10,000 feet fence at a cost of $10.00 per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and with 50% of work completed $45,000.00 has been spent. Calculate the following and submit the exercise results in a Word document, Budget at Completion (BAC) = #feet fence "cost foot Planned Value (PV) BAC* (time passed) Eamed Value (EV) BAC completed Actual Cost (AC) Cost Variance (CV) EV- AC Schedule Variance (SV) EV-PV Cost Performance Index (CPI) EVIAC % Schedule Performance Index (SPI) EV.PV % Estimate at Completion (EAC) BAC CPI Estimate to Complete (ETC) EAC-AC Variance Completion (VAC) BAC-EAC To Complete Performance Index BAC-EVI BACIAC)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts