Question: The directional demand and capacity for one freeway section is shown. Estimate the average delay cost for 10-min interval during the three hours ( the
The directional demand and capacity for one freeway section is shown. Estimate the average delay cost for 10-min interval during the three hours ( the unit cost is:$10/veh-hr)r
Hours 7~8am 8~9am 9~10am Demand 6000 4000 5000 Capacity 4500 4500 4500
Step by Step Solution
3.49 Rating (166 Votes )
There are 3 Steps involved in it
ANSWER The average delay ... View full answer