Question: The durations and direct costs for each activity under both normal and crash conditions are given in the following table. Establish the schedule and
The durations and direct costs for each activity under both normal and crash conditions are given in the following table. Establish the schedule and the least cost for expediting the contract. Determine the optimum cost of the contract assuming the indirect cost is 125 $/day. 1 2 3 4 5 6 7 00 8 9 ID Predecessor(s) 1 1 2 2 3 3,5 6 4,7,8 Normal Duration (days) 12 00 15 23 5 5 20 13 12 Cost ($) 7000 5000 4000 5000 1000 3000 6000 2500 3000 Crash Duration (days) 10 6 12 23 4 4 15 11 10 Cost ($) 7200 5300 4600 5000 1050 3300 6300 2580 3150