Question: The earliest expected finish time for a project is 1 3 8 days, and its required completion time is 1 3 0 days. What is

The earliest expected finish time for a project is 138 days, and its required completion time is 130 days. What is the chance of completing the project by its required time if the standard deviation of the total distribution of activities on the longest path, =6?