Question: The earliest expected finish time for a project is 138 days, and its required completion time is 130 days. What is the probability of completing

The earliest expected finish time for a project is 138 days, and its required completion time is 130 days. What is the probability of completing the project before its required time if σt (the standard deviation of the total distribution of the activities on the longest path) is 6?

Step by Step Solution

3.38 Rating (173 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Z 130 138 6 133 The probability of completing the project betw... View full answer