Question: The earned value of the project can be calculated using the formula: Earned Value = Percentage Complete Estimate at Completion Given the information provided: Current
The earned value of the project can be calculated using the formula: Earned Value = Percentage Complete Estimate at Completion Given the information provided: Current percentage complete = 35% Estimate at completion = $40,622,197 Substitute these values into the formula: Earned Value = 0.35 $40,622,197 Earned Value = $14,217,218.95 Therefore, the earned value of the project is approximately $14,217,219. Analyze project perfomance