Question: The earned value to date divided by the plan ned value of work scheduled to be performe d is the ( ) . cost performance
The earned value to date divided by the plan ned value of work scheduled to be performe is the
cost performance index
budgeted cost at completion index
budget efficiency index
schedule performance index