Question: he earned value to date divided by the planned value of work scheduled to be performed is the: Group of answer choices Cost performance index.

he earned value to date divided by the planned value of work scheduled to be performed is the:
Group of answer choices
Cost performance index.
Budgeted cost at completion index.
Budget efficiency index.
Schedule performance index.