Question: The end product J is made from components K and L . The authorized MPS calls for 2 0 0 J to be completed in

The end product J is made from components K and L. The authorized MPS calls for 200 J to be completed in week 3,300 J to be completed in week 5, and 300 J to be completed in week 6. There is a scheduled receipt of 400 L in week 2. What are the planned orders for K and L?