Question: The equation for the PERT _?_ average is: (optimistic time + 4(most likely time) + pessimistic time)/6. Group of answer choices weighted slack constraint probabilistic
The equation for the PERT _?_ average is: (optimistic time + 4(most likely time) + pessimistic time)/6. Group of answer choices
weighted
slack
constraint
probabilistic