Question: The ES for Activity C is _ _ _ _ _ ? a ) 1 0 b ) 3 c ) 1 4 d )

The ES for Activity C is _____?
a)10
b)3
c)14
d)8
2. The LS for Activity E is _____?
a)12
b)9
c)14
d)15
3. What is the project duration _____?
a)12
b)15
c)14
d)25
4. The slack for the start of Activity G is____?
a)15
b)10
c)0
d)25
5. The slack for the start of Activity B is____?
a)9
b)4
c)3
d)2
6. The slack for the start of Activity E is____?
a)0
b)1
c)15
d)29
7. The slack for the finish of Activity G is____?
a)15
b)0
c)25
d)5