Question: 1) The ES for Activity C is ________. [A] 2) The LS for Activity E is ________. [B] 3) The LS for Activity G is
![1) The ES for Activity C is ________. [A] 2) The](https://dsd5zvtm8ll6.cloudfront.net/si.experts.images/questions/2024/09/66f3a3d755143_22266f3a3d6cf67c.jpg)
1) The ES for Activity C is ________. [A]
2) The LS for Activity E is ________. [B]
3) The LS for Activity G is ________. [C]
4) The slack for the start of Activity G is ______. [D]
5) The slack for the start of Activity B is ______. [E]
6) The slack for the start of Activity E is ______. [F]
7) The slack for the finish of Activity H is ______. [G]
8) The slack for the finish of Activity F is ______. [H]
9) The slack for the finish of Activity G is ______. [I]
Given the network below, computer the early, late, and slack time for each activity. B B E H 2 Lag 3 c G Lag 2 Lag 4 2 Lag 3 D F Lag 2 Lag 5 2 on Legend ESD EF SL SL LS DUR LF The ES for Activity Cis The LS for Activity is The LS for Activity is The slack for the start of Activity G is The slack for the start of Activity Bis The slack for the start of Activity E is. The slack for the finish of Activity His The slack for the finish of Activity F is. The slack for the finish of Activity G is. Submit your network diagram with the early, late and slack time for each activity as an attachment