Question: The estimated activity resources will also be used later for estimating activity costs and determining the project budget. a. True b. False NSWER:True FEEDBACK:CorrectThe estimated
The estimated activity resources will also be used later for estimating activity costs and determining the project budget. a. True b. False NSWER:True FEEDBACK:CorrectThe estimated activity resources will also be used later for estimating activity costs anddetermining the project budget. IncorrectThe estimated activity resources will also be used later for estimating activity costs anddetermining the project budget. POINTS:1 DIFFICULTY:Easy QUESTION TYPE:True / False HAS VARIABLES:False LEARNING OBJECTIVES:SUPM.GIDO.15.05.01 - 1. Estimate the resources required for activities NATIONAL STANDARDS:United States - BUSPROG: Communications KEYWORDS:Bloom's: Knowledge DATE CREATED:4/5/2016 10:13 AM DATE MODIFIED:4/5/2016 10:13 AM