Question: the EV reporting for level of effort activities is based on the following Budget Earned Account Code PV EV 03110 Formwork 4,000 6,000 03210 Rebar
the EV reporting for level of effort activities is based on the following

Budget Earned Account Code PV EV 03110 Formwork 4,000 6,000 03210 Rebar 10 900 03310 Place & Finish 800 640 1,600 Subtotal Slabs at grade O a. EV (BCWP) is equal to actual cost (ACWP): no cost variations can exist EV (BCWP) is equal to quantity installed None of these choices O d. EV (BCWP) is equal to scheduled (BCWS); no schedule variations can exist O b. O c. UOM SF Ton CY Budget Quantity Total Actual Quantity To-Date 3,000 Percent Complete