Question: The Fence Project #1 (Each question is worth five points) You have been assigned to build a new fence around a garden. The fence will


The Fence Project #1 (Each question is worth five points) You have been assigned to build a new fence around a garden. The fence will end up forming a square. It will take a day to complete each side. $1,000 has been budged for each side. Only one side can be complete at a time. When one side is complete, you can start on the next side. It is now the end of day 3. Use the following char to calculate PV, EV, AC, BAC, CV, CPI, SV, SPI, EAC, ETC, and VAC. Day 1 S--------F Day 2 Day 3 Activity Side 1 Side 2 Side 3 Side 4 S--- -PF ----F PS--S---PF Day 4 Status end of Day 3 Complete, spent $1,000 Complete, spent $1,200 50% done, spent $600 PS-------PF Not yet started Key: S = Actual Start, F = Actual Finish, PS = Planned Start, PF = Planned Finish PV Calculation Answer $1,000 plus $1,000 $3,000 plus $1,000 Interpretation of Answer We expect to have $3,000 worth of work after 3 days 1. EV 2. AC 3. BAC 4. CV 5. CPI 6. SV 7. SPI 8. EAC 9. ETC 10. VAC The Fence Project #2 (Each question is worth five points) You have been assigned to build a new fence around a garden. The fence will end up forming a square. It will take a day to complete each side. $1,000 has been budged for each side. While originally scheduled to be completed one side at a time, things have changed. The work on the sides can now be processed in parallel. Assume the sides have a finish-to-finish relationship instead of a start-to-finish relationship, so more than one side can be worked on at the same time. It is now the end of day 3. Use the following char to calculate PV, EV. AC, BAC, CV, CPI, SV, SPI. EAC. ETC. and VAC. Day 2 Day 1 S-------- Day 3 Activity Side 1 Side 2 Side 3 Side 4 S-F---PF S--- Day 4 Status end of Day 3 Complete, spent $1,000 Complete, spent $900 50% done, spent $600 PS --PF | 75% done, spent $600 PS-------PF S--- Key: S= Actual Start, F = Actual Finish PS = Planned Start. PF = Planned Finish PV Calculation Answer $1,000 plus $1,000 $3,000 plus $1,000 Interpretation of Answer We expect to have $3,000 worth of work after 3 days 1. EV 2. AC 3. BAC 4. CV 5. CPI 6. SV 7. SPI 8. EAC 9. ETC 10. VAC