Question: The Fence Project #2 (Each question is worth five points) You have been assigned to build a new fence around a garden. The fence will

The Fence Project #2 (Each question is worth five

The Fence Project #2 (Each question is worth five points) You have been assigned to build a new fence around a garden. The fence will end up forming a square. It will take a day to complete each side. $1,000 has been budged for each side. While originally scheduled to be completed one side at a time, things have changed. The work on the sides can now be processed in parallel. Assume the sides have a finish-to-finish relationship instead of a start-to-finish relationship, so more than one side can be worked on at the same time. It is now the end of day 3. Use the following char to calculate PV, EV, AC, BAC, CV, CPI, SV, SPI, EAC, ETC, and VAC. Day 3 Activity Day 1 Day 2 Day 4 Status end of Day 3 Side 1 SF Complete, spent $1,000 Side 2 S-FPF Complete, spent $900 Side 3 S PSPF 50% done, spent $600 Side 4 S. PS-------PF 75% done, spent $600 Key: S = Actual Start, F = Actual Finish. PS = Planned Start, PF = Planned Finish PV Calculation Answer $1,000 plus $1,000 $3,000 plus $1,000 Interpretation of Answer We expect to have $3,000 worth of work after 3 days 1. EV 2. AC 3. BAC 4. CV 5. CPI 6. SV 7. SPI 8. EAC 9. ETC 10. VAC

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!