Question: The figure below is an Activity on Arrow ( AOA ) network diagram for a project. The lettered A through G represents an activity as

The figure below is an Activity on Arrow (AOA) network diagram for a project. The lettered A through G represents an activity as shown in the accompanying precedence diagram. The deterministic time for each activity is in the node.
Please answer the following questions:
1) Which path is the critical path? What is the length of the expected time of the project?
2) Determine the following quantities for each activity: the earliest start time, the latest start time, the earliest finish time and the latest finish time and the slack time.Please present your answer in a table.