Question: The final assembly schedule ( FAS ) : I . is basically the same as the MPS for a make - to - order product.
The final assembly schedule FAS:
Iis basically the same as the MPS for a maketoorder product.
II schedules customer orders as they are received based on components planned in the MPS
I. The production plan.
II Customer orders.
III. The rough cut capacity plan.