Question: The first image is the given info. Could you help me answer E and F please? Thanks Was told that the question wasn't visible. The

 The first image is the given info. Could you help meanswer E and F please? Thanks Was told that the question wasn't

The first image is the given info. Could you help me answer E and F please? Thanks

Was told that the question wasn't visible. The numbers 1-9 are the given information. I just need some help with the problem E and F.

Question # 2 A summary of the facts: 1. Original project cost: $1,250,000 2. Original project schedule: 10 months 3. Planned value: $740,000 at 4 months 4. Actual cost: $770,000 at 4 months 5. Earned value: $680,500 at 4 months 6. Current monthly staff: 5 people 7. Current monthly overheads: a. $23,000 per month for salaries, b. $12,300 per month for project overheads, and c. $4,900 per month for General overheads. 8. Contractual Liquidated Damages (LDs)$5,000 per day of delay 9. Assume that 1 month is 30 days e. What is the projected total cost Estimate at Completion (ECAC) neglecting any extra overheads? i. If we assume cost variance was atypical (and the rest of the project will go as originally planned)? ii. If we assume cost variance was typical (and the rest of the project will have a proportional variance)? f. What is the projected schedule Estimate at Completion (EDAC)? i. If we assume schedule variance was atypical (and the rest of the project will be as originally planned)? ii. . If we assume schedule variance was typical (and the rest of the project will have a proportional variance)? Question # 2 A summary of the facts: 1. Original project cost: $1,250,000 2. Original project schedule: 10 months 3. Planned value: $740,000 at 4 months 4. Actual cost: $770,000 at 4 months 5. Earned value: $680,500 at 4 months 6. Current monthly staff: 5 people 7. Current monthly overheads: a. $23,000 per month for salaries, b. $12,300 per month for project overheads, and c. $4,900 per month for General overheads. 8. Contractual Liquidated Damages (LDs)$5,000 per day of delay 9. Assume that 1 month is 30 days e. What is the projected total cost Estimate at Completion (ECAC) neglecting any extra overheads? i. If we assume cost variance was atypical (and the rest of the project will go as originally planned)? ii. If we assume cost variance was typical (and the rest of the project will have a proportional variance)? f. What is the projected schedule Estimate at Completion (EDAC)? i. If we assume schedule variance was atypical (and the rest of the project will be as originally planned)? ii. . If we assume schedule variance was typical (and the rest of the project will have a proportional variance)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!