Question: The first step in the control cycle is: A . Taking action. B . Measuring progress. C . Comparing actual with planned performance. D .

The first step in the control cycle is:
A. Taking action.
B. Measuring progress.
C. Comparing actual with planned performance.
D. Setting a goal.
 The first step in the control cycle is: A. Taking action.