Question: The following 10 data points for the Schedule Performance Index (SPI) were measured for a project: 1, 1, 1, 1, 1, 1, 5, 3, 4,
-
The following 10 data points for the Schedule Performance Index (SPI) were measured for a project: 1, 1, 1, 1, 1, 1, 5, 3, 4, 2. What is the value for the centerline in the X-Chart?
-
3
-
1
-
2.5
-
2
-
-
What is the value for the Mean in the mR-Chart of the 10 SPI data points: 1, 1, 1, 1, 1, 1, 5, 3, 4, 2?
-
1
-
1.5
-
0.75
-
0.5
-
-
For the questions above, the UNPL (Upper Natural Process Limit) is 4.66. Is the project schedule execution in control?
-
Yes.
-
It is not possible to say.
-
It depends on the perspective.
-
No, because at least one WE rule is violated.
-
-
If one data point out of 50 process measures is above the UNPL the process ______.
-
needs to be further investigated.
-
is under specific conditions in control.
-
is still in control.
-
is not in control because one WE rule is violated.
-